Milestone of KEK Proton Synchrotron
summarized by H. Sato
1971 | Apr. | Construction Start |
1974 | June | 750 KeV Pre-Accelerator |
Aug. | 20 MeV LINAC | |
Dec. | Booster Accelerated up to 500 MeV | |
1975 | Dec. | MR Injection |
1976 | Mar. |
MR Accelerated up to 8 GeV (Original Design) |
July | Utility Start Using Internal Target | |
Dec. | MR 12 GeV | |
1977 | Jan. | Fast Extraction to EP1 Line |
May | Utility Start for Bubble Chamber Experiment | |
June | BSTR Intensity 6 x 1011 ppp | |
Nov. | Slow Extraction to EP2 Line and Utility Start | |
1978 | July | MR Intensity 2 x1012 ppp |
1980 | Jan. | MR Intensity 2.85 x 1012 ppp |
May | MR Intensity 4.07 x 1012 ppp | |
June | Utility Start to Booster Facility | |
1981 | July | Shut Down of Fast Extraction |
Dec. | MR Intensity 4.1 x 1012 ppp | |
1983 | Nov. | H- Injection to Booster |
Polarized Proton Beam Acceleration Test Start | ||
1984 | Long Shut Down due to TRISTAN Construction | |
May | Replace of Preaccelerator Tube | |
1985 | Nov. | LINAC Upgrade to 40 MeV |
1986 | May | Pulse Sharing Operation of Normal Intensity Beam and Polarized Proton Beam |
1987 | May | Utility Start Using Polarized Proton Beam |
1988 | May | Replace of Control System from Melcom to VME |
1989 | June | MR Intensity 5.4 x 1012 ppp (max.) |
1990 | May | BSTR Intensity 2.4 x 1012 ppp |
Aug. | MR Power Supply Upgrade for the Flat Top Extension | |
Sep. | Replace of EP1, EP2 Extraction system | |
Realignment of the main ring Q magnets (vertical) | ||
Oct. | EP2 Spill Length of 2 sec | |
1991 | Jan. | Slow Extraction to EP1 |
May | Start of Deuteron Beam Acceleration Test | |
1992 | Jan. | Accelerated and Extracted of Deuteron Beam at 11.2GeV |
Apr. | Utility Start Using Deuteron Beam | |
Variable Energy Extraction | ||
1994 | Apr. | Septum-bump injection system was developed |
Acceleration Test of aƒ¿-Beam and Utility Start at 23GeV | ||
Aug. | Realignment of the booster magnets | |
Nov. | MR Intensity 5.95 x 1012 ppp (max.) | |
1995 | Feb. | Study for the Intensity Upgrade |
1996 | Mar. | Polarized Duteron Beam Accelerator Test |
Sep. | B-Q Duct and BPM Replacement (partially) | |
Realignment of the main ring Q magnets (vertical, partially) | ||
Oct. | MR Intensity 5.5-6.1 x 1012 ppp (20 min. AV) | |
1997 | Upgrade of the Pulsed Quarupole Power Supply for the Transition Crossing | |
Studies for the Beam Loss at the Acceleration Start | ||
Fast Kicker Magnets Design and Construction | ||
1998 | June | MR Intensity 4.7-4.9 x 1012 ppp during utility run |
Half Year Shut Down for the Preparation of the Long Base Line Nuetrino Experiment | ||
Installation of the Fact Kicker Magnets | ||
Replace of the Septum Magnets Power Supply | ||
1999 | Feb. | Fast Extracted Beam to the Production Target Position |
Mar. | Comissioning start of the Long Base Line Neutrino Experiment | |
May | MR Intensity 6.2 x 1012 ppp | |
June | MR Intensity 6.8 x 1012 ppp | |
2000 | Mar. | MR Intensity 8.0 x 1012 ppp |
2001 | Oct. | Booster Power Supply Upgrade |
2003 | July | Induction Acceleration Study |
2005 | Jan. | Fast Extraction End |
2005 | Dec. | Main Ring Utility End |
2006 | Mar. | Booster Utility End |